[Announcement of Draft for Comments] Nantong Taiyang High-tech Materials Technology Co., Ltd.’s 812-ton annual fluoride expansion and safety and environmental protection improvement project

Announcement of the draft environmental impact assessment of Nantong Taiyang High-tech Materials Technology Co., Ltd.'s 812-ton annual fluoride expansion and safety and environmental improvement project

 

In accordance with the relevant requirements of the "Measures for Public Participation in Environmental Impact Assessment" (Ministry of Ecology and Environment Order No. 4), a draft environmental impact report for this project has been formed. The following information is now disclosed to solicit opinions related to the environmental impact of this construction project:


1. Project name and summary

Project name: Annual output of 812 tons of fluoride expansion and safety and environmental protection improvement project

Construction unit: Nantong Taiyang High-tech Materials Technology Co., Ltd.

Construction location: On the east side of Tongshun Road, Nantong Economic and Technological Development Zone, on the south side of Jiangshan Road, within the existing factory area of Nantong Taiyang High-tech Materials Technology Co., Ltd.

Project nature: Renovation and expansion

Construction scale and content: Add reactors, centrifuges, microwave drying tunnel furnaces and other equipment, and use the existing main engineering, production equipment, public auxiliary facilities, etc. to add fluoride production capacity of 812t/a; and upgrade existing environmental protection facilities Improvement and transformation. After the completion of this project, the total fluoride production capacity of the entire plant can be achieved at 847.8t/a.


2. Online link to the full text of the environmental impact report solicitation draft and ways and means of accessing the paper report

Draft Environmental Impact Report for Comments: See Attachment 1;

Methods and channels for reviewing paper reports: Contact the construction unit via email, phone, etc. to review paper reports.


3. Public scope for soliciting opinions

The scope of soliciting public opinions: the public around the project location who are concerned about the construction of the project.

Main matters for soliciting public opinions: From an environmental protection perspective, what is your attitude towards this project or its environmental impact report? Please briefly explain the reasons.


4. Online link to the public comment form

After this information is disclosed, the public can download the public opinion form in the attachment on this page. (See Attachment 2).


5. Methods and channels for the public to submit opinions

The public can feedback the completed public opinion form to the construction unit within the specified time by letter, fax, email or phone call to reflect the opinions and suggestions related to the environmental impact of the construction project (Note: According to the "Public Participation in Environmental Impact Assessment" The Measures stipulate that opinions or demands related to land acquisition and demolition, property, employment, etc. that have nothing to do with the project environmental impact assessment are not part of the project environmental impact assessment public participation content). Members of the public who express opinions should indicate the date of publication, real name and contact information so that they can provide feedback if necessary.


6. Starting and ending time for public opinions

Within 10 working days from the date of this announcement, the public can feedback the completed public opinion form to the construction unit or environmental assessment unit within the specified time by letter, fax, email or phone call. When the public submits opinions, please provide valid contact information so that a follow-up visit can be made if necessary.


7. Contact information

Name of construction unit: Nantong Taiyang High-tech Materials Technology Co., Ltd.

Unit address: Nantong Economic and Technological Development Zone, east of Tongshun Road, south of Jiangshan Road, Nantong

Contact person: Manager Zhou

contact number:0513-89197920

Environmental impact assessment unit: Jiangsu Runhuan Environmental Technology Co., Ltd.

Address: 14th Floor, Jinjian Building, No. 64, Shuizuogang, Gulou District, Nanjing

Contact person: Chen Gong

contact number:025-85303391

Email: purple0525@foxmail.com


Nantong Taiyang High-tech Materials Technology Co., Ltd.


1682561986103568.docx

Attachment 1: Draft for comments on Nantong Taiyang High-tech Materials Technology Co., Ltd.’s annual 812-ton fluoride expansion and safety and environmental improvement project.pdf